IDCanalFromToStart DateEnd DateDescription ( Click to see original C&RT Notice )Last Updated

29181Anderton LiftAnderton Lift (River Weaver)Anderton Lift (Trent and Mersey)03 January 202506 November 2026Earlier this year, the Anderton Boat Lift was closed after a lifting wire failure during planned routine maintenance by our teams. Unfortunately, it is not possible to reopen the lift using the existing gate lifting system. Trust engineers have been working closely with specialist consultants to develop a solution that will see the original rope-and-pulley mechanism replaced on all gates with a more modern, robust and safer lifting system making the lift more reliable.

We're pleased to confirm that the Trust has prioritised the funding required to support the detailed engineering design. However, this work will take time, and the lift will remain closed throughout all next year 2026. We understand how frustrating this closure will be for boaters who regularly use this vital link between the Weaver Navigation and the rest of the Trust's network. The significant investment we're making into this repair reflects how important the lift is to our waterways. Although the lift itself will stay closed, the Anderton Boat Lift Visitor Centre will remain open, with an exciting programme of events and activities planned for 2026. We hope you'll continue to visit and enjoy everything the site has to offer.

This essential redesign work is being delivered ahead of, and separately from, the wider refurbishment programme. We'll continue to share updates as the project progresses.

We also understand the impact that Marsh Lock's closure is having on customers wanting to visit the Weaver. Our teams are working through the options to bring the lock back into operation, and you can follow updates [here.](

Thank you for your ongoing patience and support for this vital and historic structure.
06 November 25 19:15:52

IDCanalFromToStart DateEnd DateDescription ( Click to see original C&RT Notice )Last Updated

29729Grand Union Canal (Grand Junction Canal - Main Line - Gayton to Brentford)Marsworth Lock No 42Marsworth Lock No 4206 January 202613 March 2026Please be advised that the towpath will no longer be closed during these works.07 January 26 12:00:01

29821Grand Union Canal (Grand Junction Canal - Main Line - Gayton to Brentford)Batchworth Lock No 81Batchworth Lock No 8109 January 202620 February 2026Following the dewatering of the navigation, further essential work has been identified to ensure this repair can be completed safely and to the correct standard. As a result, the current stoppage will need to be extended.
During the inspection, a section of approximately 12 metres of the existing wall was found to be in significantly worse condition than originally anticipated. This section must be fully dismantled so that new foundations can be installed, before the wall can be rebuilt.
The navigation is now scheduled to reopen on 20 February 2026. These works will be completed by this date, and passage will be made available over the following weekend, ahead of the next planned stoppage at Lotmead Lock 80, which begins on 23 February 2026.
We apologise for any inconvenience this extension may cause and thank you for your patience while we complete this essential repair.
26 January 26 14:00:05

29814Grand Union Canal (Grand Junction Canal - Main Line - Gayton to Brentford)Fenny Stratford Lock No 22Soulbury Top Lock No 2602 February 202620 February 2026Due to high water levels in the area, the start of the planned stoppage has had to be rescheduled to 02/02/2026. We will be working to claw back the lost time and the end date will remain unchanged.
We apologise for the short notice of this change and thank you for your understanding.
27 January 26 16:00:06

29594Grand Union Canal (Grand Junction Canal - Main Line - Gayton to Brentford)Northchurch Lock No 51Northchurch Lock No 5103 February 202604 February 2026A dewatered lock head is required to replace a broken ground paddle post, this will require stop plank installation, the stoppage will start at lock 51 for water control and safety purposes.

Navigation closed, Towpath remains open.
07 December 25 19:56:56

29595Grand Union Canal (Grand Junction Canal - Main Line - Gayton to Brentford)Berkhamsted Middle Lock No 54Berkhamsted Middle Lock No 5410 February 202611 February 2026A dewatered lock head is required to replace broken tow path Ground paddle post at lock 55, the stoppage will start at lock 54 for water control and safety purposes.

Navigation will be closed, tow path remains open
07 December 25 19:57:02

IDCanalFromToStart DateEnd DateDescription ( Click to see original C&RT Notice )Last Updated

29945Leeds and Liverpool Canal (Main Line - Wigan to Leeds)Wigan Bottom Lock No 85Wigan Top Lock No 6505 January 202613 March 2026Please be advised that, in addition to the advertised works at Locks 81 and 65, we will also be carrying out repair works at Lock 75, which require the lock to be dewatered.
The stoppage dates and closure location remain unchanged as originally communicated. Both teams have coordinated to ensure these works can proceed safely and efficiently. Measures will be in place to maintain water flow past the work sites and manage lock flight control effectively.
We appreciate your understanding and cooperation while these important improvements are completed.
16 January 26 21:29:26

28906Leeds and Liverpool Canal (Main Line - Wigan to Leeds)Wigan Lock No 83Wigan Lock No 8319 January 202620 February 2026Following a review of the works, this stoppage has been extended until 20 February to allow for additional tasks identified on site. We will now be carrying out grouting works to both lock chambers and the upstream approach walls. Please note that the Wigan Flight will already be closed in this area, and these works will be undertaken alongside the originally planned works at other locations on the flight.28 November 25 12:00:05

30093Leeds and Liverpool Canal (Main Line - Wigan to Leeds)Eshton Road Lock No 31Eshton Road Lock No 3109 March 202631 March 2026Essential paddle works are required at Eshton Road Lock 31. To ensure the repairs can be completed safely and effectively, a navigation restriction will be in place for the duration of the works. These works are necessary to maintain the continued reliability and safe operation of the lock. 
The navigation will remain open during this time, but boats may be asked to wait briefly while the site is made safe for passage.
Thank you for your understanding and patience.
02 February 26 19:11:20

IDCanalFromToStart DateEnd DateDescription ( Click to see original C&RT Notice )Last Updated

19378Middle Level Navigations (Forty Foot River)Welches Dam SluiceWelches Dam Sluice13 October 202312 October 2099This lock is closed permanently.13 October 23 19:19:13

IDCanalFromToStart DateEnd DateDescription ( Click to see original C&RT Notice )Last Updated

29735Shropshire Union Canal (Llangollen Canal - Main Line)Grindley Brook Bottom Lock No 14Whitchurch Ring Road Bridge No 31A22 December 202523 January 2027We are pleased to report that the three boats most impacted by the breach have now been recovered and refloated. Our focus will now turn to the work required to rebuild the canal and reopen it as soon as possible.

Given the size and scale of the repair to reinstate the canal, work is unfortunately expected to continue for much of 2026. We appreciate that some boaters on the stretch of canal north of the breach may wish to move their boat before the canal repairs are complete and are grateful that Whitchurch Marina is providing the option for boats to be moved before the breach is repaired.

Engineering investigations into the cause of the breach are ongoing, and we will publish a summary of our findings once complete. For further information, please see our FAQs regarding the breach below:

[Llangollen Canal breach boating FAQs | Canal & River Trust](
23 January 26 14:02:48

30043Shropshire Union Canal (Llangollen Canal - Main Line)New Marton Top Lock No 1New Marton Top Lock No 109 February 202627 February 2026We need to introduce an emergency stoppage at Lock 1, New Marton, above Welsh Frankton, on the Llangollen Canal to allow essential repair works to be carried out.
The bottom gate has developed a serious water leak, which is preventing the lock from filling correctly. Repairs are required to the lock gates and cill, along with associated brickwork restoration.
Given the impact on boats currently within the now‑isolated length of canal, we are keen to undertake these repairs now, ahead of the main boating season, to minimise longer‑term disruption.
The stoppage will be in place from 9 February until 27 February.
We apologise for any inconvenience this may cause and thank you for your understanding while we complete these vital works.
28 January 26 18:49:00

IDCanalFromToStart DateEnd DateDescription ( Click to see original C&RT Notice )Last Updated

26642Grand Union Canal (Leicester Section - Old Grand Union)Watford Bottom Lock No 1Watford Top Lock No 729 March 202502 May 2026Watford Lock Flight Opening Times:

29th March 2025:


Flight open 09:30am, last boat in at 2:45pm


30th March 2025 - 28th June 2025


Flight open 8am, last boat in at 5pm


29th June 2025 - 13th September 2025


Flight open 8am, last boat in at 6pm


14th September 2025 - 25th October 2025


Flight open 8am, last boat in at 5pm


26th October 2025 - 28th March 2026


Flight open 09.30am, last boat in at 3pm


Please ensure you have booked in with the lock keeper before you enter Lock 1 or 7.


The lock keeper will either be on the flight, or in the Top Lock Keepers Hut.


If you enter the Locks without booking in, you may be required to back out, as other boats may be working the flight.


Please follow any advice given by Trust representatives on site.












06 May 25 19:24:58

26643Grand Union Canal (Leicester Section - Old Grand Union)Foxton Bottom StaircaseFoxton Top Staircase29 March 202502 May 2026Foxton Lock Flight Opening Times:

29th March 2025:


Flight open 09:30am, last boat in at 2:45pm


30th March 2025 - 28th June 2025


Flight open 8am, last boat in at 5pm


29th June 2025 - 13th September 2025


Flight open 8am, last boat in at 6pm


14th September 2025 - 25th October 2025


Flight open 8am, last boat in at 5pm


26th October 2025 - 28th March 2026


Flight open 09.30am, last boat in at 3pm


Please ensure you have booked in with the lock keeper before you enter Lock 8 or 17.


The lock keeper will either be on the flight, or in the Top Lock Keepers Hut.


If you enter the Locks without booking in, you may be required to back out, as other boats may be working the flight.


Please follow any advice given by Trust representatives on site.












06 May 25 19:24:58

IDCanalFromToStart DateEnd DateDescription ( Click to see original C&RT Notice )Last Updated

27557Lee and Stort Navigation (River Lee)Ware Lock No 2Ware Lock No 217 May 202506 November 2026If you are using Ware Lock, this unmanned structure is owned by the Environment Agency who have issued guidance to help boaters avoid getting stuck.

LOCK OPERATION – Please Follow the below guidance to operate the lock
 
For Craft going upstream towards Hertford.
1.      Open the sluices to drain the lock to low level.
2.      Open the Downstream gates
3.      Manoeuvre your craft into the basin
4.      Close the gates
5.      ENSURE that the Sluice is fully closed for both downstream gates ( see picture below)
6.      Open the upstream sluices and allow the basin to fill
7.      Close the upstream sluice
8.      Open the gates
Failure to check Point (5) may result in having to drain the basin and start again.

For Craft travelling away from Hertford
1.      Ensure that the downstream gates are closed
2.      Close the Sluices of the downstream gates (this MUST be done when the chamber is at low level)
3.      Check the Slice marker (picture above) is fully closed
4.      Open the Upstream sluices  
5.      Fill the basin
6.      Open the gates and manoeuvre the craft into the lock basin
7.      Close the Upstream sluice and gates
8.      Open the downstream sluice drain the basin
9.      Open the gates and manoeuvre the craft out of the lock
06 November 25 19:15:20

IDCanalFromToStart DateEnd DateDescription ( Click to see original C&RT Notice )Last Updated

29082Leeds and Liverpool Canal (Main Line - Wigan to Leeds)Bank Newton Top Lock No 41Kirkstall Forge Staircase Locks Nos 8 to 1009 October 202519 December 2026As we move into Winter Hours, the both locks listed below must now be booked at least 72 hours in advance. This year, Newlay and Forge have been added to the winter-hours booking schedule alongside 3 & 5 Rise.
Winter hours run from Monday 1st December to Tuesday 31st March 2026.
 
3 & 5 Rise – Booking Arrangements
Up the flight
 
* Monday, Wednesday, Friday, Sunday
* Booking slots: 9:00–10:00 and 10:00–11:00
 
Down the flight
 
* Monday, Wednesday, Friday, Sunday
* Booking slots: 11:00–12:00 and 12:00–13:00
 
Please use the online booking system on our website to book passage.
Bookings must be made at least 72 hours before travel — no late bookings can be accepted.
Wide Beam Vessels:
If your boat is over 7ft wide, you must book directly with our Yorkshire & North East Customer Service Team, as wide beams require separate passage and cannot share lock space.
Call 03030 404040 (Mon–Fri, 8:00–16:30) with at least 72 hours' notice.
 


Newlay & Forge – Booking Arrangements

To book Newlay & Forge,
Please use the online booking system on our website to book passage.
Bookings must be made at least 72 hours before travel — no late bookings can be accepted.

Wide Beam Vessels:
If your boat is over 7ft wide, you must book directly with our Yorkshire & North East Customer Service Team, as wide beams require separate passage and cannot share lock space.
Call 03030 404040 (Mon–Fri, 8:00–16:30) with at least 72 hours' notice.
 
 
Available booking days and times:
  Tuesday: Down the flight from 9:00–11:00, Up the flight from 11:00–13:00
  Thursday: Down the flight from 9:00–13:00, Up the flight from 11:00–13:00
  Saturday: Down the flight from 9:00–13:00, Up the flight from 11:00–13:00
 
A minimum of 72 hours' notice is required for all winter-hours bookings.
We will review these arrangements as the season progresses.
If you need any further information, feel free to give us a call. Thanks for your help.
19 December 25 12:00:02

IDCanalFromToStart DateEnd DateDescription ( Click to see original C&RT Notice )Last Updated

26514Trent and Mersey Canal (Main Line - Etruria to Hardings Wood)Harecastle Tunnel (northern entrance)Harecastle Tunnel (southern entrance)01 March 202502 May 2026Harecastle Tunnel Summer opening times from 1st March 2025 to 31st October 2025:

Open passages are available from 8am to 12 noon, Monday to Sunday. Un-booked (Open) passages must arrive at the tunnel portal between 8am and 12 noon. There is no guarantee of passage for arrivals after 12 noon unless pre-booked the day before by booking Alternatively, please contact our customer services department on 0303 0404040.


Bookable passages are available Southbound (Kidsgrove to Tunstall) at 2pm and 4pm and Northbound (Tunstall to Kidsgrove) at 1pm and 3pm.


For direct tunnel enquiries please email eventsnorthstaffs@canalrivertrust.org.uk


Please always follow the directions of our team members on site. Passage is only permitted with a working horn and tunnel light; at present we are unable to lend such items.












06 May 25 19:24:56

29306Trent and Mersey Canal (Main Line - Etruria to Hardings Wood)Harecastle Tunnel (northern entrance)Harecastle Tunnel (southern entrance)01 November 202528 February 2026Please note the available passage times for Harecastle Tunnel over the Christmas period are as follows:

* Monday 22nd: 9:00am – 12:00 noon
* Tuesday 23rd: Closed
* Wednesday 24th: Closed
* Thursday 25th Closed
* Friday 26th: Closed
* Saturday 27th: 9:00am – 12:00 noon
* Sunday 28th: Closed
* Monday 29th: 9:00am – 12:00 noon
* Tuesday 30th: Closed
* Wednesday 31st: Closed
* Thursday 1st: Closed
* Friday 2nd: Closed
* Saturday 3rd: 9:00am – 12:00 noon
16 December 25 13:00:04

30041Trent and Mersey Canal (Main Line - Etruria to Hardings Wood)Harecastle Tunnel (northern entrance)Harecastle Tunnel (northern entrance)01 March 202631 October 2026Harecastle Tunnel Summer opening times from 1 March 2026 to 31 October 2026:

All passages must be pre-booked 48hrs before passage [online]( . There is no guarantee of passage for boats unless pre-booked. 

Bookable passages are available:

* Southbound (Kidsgrove to Tunstall) at 8am, 10am, 12pm, and 2pm
* Northbound (Tunstall to Kidsgrove) at 9am, 11am, 1pm and 3pm

If you turn up earlier than your booked slot, the Tunnel Keepers will do their best to get you through. Alternatively, please contact us on 0303 0404040. For direct tunnel enquiries please email

Please always follow the directions of our team members on site. Passage is only permitted with a working horn and tunnel light; at present we are unable to lend such items.
28 January 26 18:49:42

IDCanalFromToStart DateEnd DateDescription ( Click to see original C&RT Notice )Last Updated

19378Middle Level Navigations (Forty Foot River)Welches Dam SluiceWelches Dam Sluice13 October 202312 October 2099This lock is closed permanently.13 Oct 23 19:19:13

25756Bridgewater Canal (Main Line)Agden Bridge No 26Dunham Town Bridge No 2702 January 202506 November 2026The Bridgewater Canal is currently closed between Agden Bridge No. 26 and Dunham Town Bridge No. 27 due to a breach. This section is managed by the Bridgewater Canal Company, not the Canal & River Trust. However, as this canal connects to our network and forms part of the Cheshire Cruising Ring, we are liaising closely with them.

Nearest Winding Holes:

* West of the Breach: Between Oughtrington Bridge No. 24 and Lymm Bridge No. 23.
* East of the Breach: Between Seamon's Moss Bridge No. 29 and Broadheath Bridge No. 30.

Canal & River Trust Customers

If any of our customers are stuck on the Bridgewater Canal, please contact our North West Customer Service Team at 0303 0404 040 for support.

Further updates will be provided as more information becomes available. For additional details, visit the Bridgewater Canal Company website: < >
06 Nov 25 19:15:18

29181Anderton LiftAnderton Lift (River Weaver)Anderton Lift (Trent and Mersey)03 January 202506 November 2026Earlier this year, the Anderton Boat Lift was closed after a lifting wire failure during planned routine maintenance by our teams. Unfortunately, it is not possible to reopen the lift using the existing gate lifting system. Trust engineers have been working closely with specialist consultants to develop a solution that will see the original rope-and-pulley mechanism replaced on all gates with a more modern, robust and safer lifting system making the lift more reliable.

We're pleased to confirm that the Trust has prioritised the funding required to support the detailed engineering design. However, this work will take time, and the lift will remain closed throughout all next year 2026. We understand how frustrating this closure will be for boaters who regularly use this vital link between the Weaver Navigation and the rest of the Trust's network. The significant investment we're making into this repair reflects how important the lift is to our waterways. Although the lift itself will stay closed, the Anderton Boat Lift Visitor Centre will remain open, with an exciting programme of events and activities planned for 2026. We hope you'll continue to visit and enjoy everything the site has to offer.

This essential redesign work is being delivered ahead of, and separately from, the wider refurbishment programme. We'll continue to share updates as the project progresses.

We also understand the impact that Marsh Lock's closure is having on customers wanting to visit the Weaver. Our teams are working through the options to bring the lock back into operation, and you can follow updates [here.](

Thank you for your ongoing patience and support for this vital and historic structure.
06 Nov 25 19:15:52

27719Sheffield and South Yorkshire Navigation (Stainforth and Keadby Canal)Vazon Road Rail Swing BridgeVazon Road Rail Swing Bridge02 June 202506 November 2026The ambient temperatures at Keadby Rail Drawbridge are reducing as we are approaching a cooler season. With these reducing temperatures, the traffic light system has been removed for the autumn/winter period. Network Rail have advised that the bridge will continue to be available for passage at any time, providing the structure temperature is 16 degrees or below06 Nov 25 19:15:23

28019Pocklington Canal (Navigable Section)Cottingwith Lock No 1Bielby Arm26 June 202519 December 2026Following some significant rainfall and the completion of works by our Direct Services team, the Pocklington Canal is now open.

Please note, however, bookings will be required for passage. Boaters must give at least 48 hours' notice by calling
03030 404040
19 Dec 25 16:00:06

28040Kennet and Avon Canal (Main Line)Brunsden Lock No 77Brunsden Lock No 7729 August 202506 November 2026Further to the notice below, please be advised that the vegetation/ root ball is still blocking the top offside ground paddle at Lock 77 Brunsden.

We kindly ask customers to be patient whilst using the lock as it will take longer to fill.

We are working to get the obstruction removed.

You are welcome to contact us at [enquiries.walessouthwest@canalrivertrust.org.uk](mailto:enquiries.walessouthwest@canalrivertrust.org.uk) or 03030 404040 if you would like to discuss this information with a member of our Customer Service Team.
06 Nov 25 19:15:26

28898River Avon (Kennet and Avon Navigation)Kelston Lock No 5Kelston Lock No 510 September 202510 October 2026Further to the notice below, please be advised that our assisted passage days at Lock 5, Kelston Lock have now finished.
However our team will be happy to support passage through the lock when we have colleagues and volunteers available.    

If you require assistance through the lock please contact us at enquiries.walessouthwest@canalrivertrust.org.uk or 03030 404040 where our team will be able to help with dates and timings.
10 Oct 25 20:11:23

28801River Weaver (Weston Marsh Lock Line)Weston Marsh LockWeston Marsh Lock12 September 202516 January 2027We are pleased to confirm that the passage on 7 January 2026 for boats travelling from the Weaver Navigation to the Shropshire Union via Marsh Lock was successfully completed. We would like to thank our customers for their continued patience and support throughout this operation.

We are now planning to provide another passage through Marsh Lock on Wednesday, 4 February 2026. Following this date, passages will be paused while our team undertakes further repair works aimed at improving future operations through the lock.

The 4 February passage is now available to book via [My Bookings]( . Please note that Marsh Lock remains open to narrowboats only, operating under single-gate manual operation.

Repair works will continue, and we will provide further updates on progress. Our aim is to complete these works in time for Easter, allowing improved access through the lock. In the longer term, our teams are continuing investigations into a more substantial refurbishment of the lock's electric motors and operational improvements, working jointly with Peel Ports.

Our next update will be issued on or before Friday, 13 February 2026.
16 Jan 26 18:00:02

29253Chesterfield Canal (Norwood to Retford)Field Bridge No 33Dog Kennels Bridge No 3131 October 202502 February 2027We continue to work closely with the Environment Agency to identify a source of the ongoing pollution. Containment measures must remain in place whilst investigations are ongoing.

Further update will be given by Monday 16th February.
02 Feb 26 15:00:05

29735Shropshire Union Canal (Llangollen Canal - Main Line)Grindley Brook Bottom Lock No 14Whitchurch Ring Road Bridge No 31A22 December 202523 January 2027We are pleased to report that the three boats most impacted by the breach have now been recovered and refloated. Our focus will now turn to the work required to rebuild the canal and reopen it as soon as possible.

Given the size and scale of the repair to reinstate the canal, work is unfortunately expected to continue for much of 2026. We appreciate that some boaters on the stretch of canal north of the breach may wish to move their boat before the canal repairs are complete and are grateful that Whitchurch Marina is providing the option for boats to be moved before the breach is repaired.

Engineering investigations into the cause of the breach are ongoing, and we will publish a summary of our findings once complete. For further information, please see our FAQs regarding the breach below:

[Llangollen Canal breach boating FAQs | Canal & River Trust](
23 Jan 26 14:02:48

29784Staffordshire and Worcestershire Canal (Main Line: Autherley to Great Haywood)Penkridge Lock No 38Penkridge Lock No 3831 December 202530 January 2027Engineers have attended site at Penkridge Lock 38 to assess the damage. A significant section of the culvert has collapsed, which has also washed out sections of infill and foundation beneath the bridge and the nearby cottage.

To prevent any further risk to these structures, the void has been stabilised using specialist concrete. Contractors are now working to clear remaining sections of the culvert that are blocked with compacted debris.

Further investigations and surveys are ongoing to establish the original alignment of the failed culvert. Once confirmed, options to reinstate the culvert, including water jetting or directional drilling through the concrete infill, will be explored.

At this stage, a reopening date cannot be confirmed and will depend on the successful installation of a new section of culvert. Further updates will be provided once investigations and surveys have progressed.
30 Jan 26 15:00:09

29600Staffordshire and Worcestershire Canal (Main Line: Stourport to Stourton)York Street Lock No 3York Street Lock No 305 January 202613 March 2026We'd like to clarify the dimensions of this stoppage. The navigation will be closed at York Street Lock, with an upstream winding hole at Whittington and a downstream winding hole at Stourport Basin.19 Dec 25 16:00:05

29945Leeds and Liverpool Canal (Main Line - Wigan to Leeds)Wigan Bottom Lock No 85Wigan Top Lock No 6505 January 202613 March 2026Please be advised that, in addition to the advertised works at Locks 81 and 65, we will also be carrying out repair works at Lock 75, which require the lock to be dewatered.
The stoppage dates and closure location remain unchanged as originally communicated. Both teams have coordinated to ensure these works can proceed safely and efficiently. Measures will be in place to maintain water flow past the work sites and manage lock flight control effectively.
We appreciate your understanding and cooperation while these important improvements are completed.
16 Jan 26 21:29:26

29797Lancaster Canal (Glasson Branch)Glasson Lock No 4Glasson Lock No 405 January 202623 January 2027Navigation remains closed at Lock 4 on the Glasson Branch, due to the rotten paddles that require a replacement.

Unfortunately we continue to wait for the replacement paddles as they are a unique design, and delivery is taking longer than anticipated.

Due to this we are unable to confirm a start date.

We will provide a further update on Friday, 6 February.
23 Jan 26 13:00:03

29729Grand Union Canal (Grand Junction Canal - Main Line - Gayton to Brentford)Marsworth Lock No 42Marsworth Lock No 4206 January 202613 March 2026Please be advised that the towpath will no longer be closed during these works.07 Jan 26 12:00:01

29821Grand Union Canal (Grand Junction Canal - Main Line - Gayton to Brentford)Batchworth Lock No 81Batchworth Lock No 8109 January 202620 February 2026Following the dewatering of the navigation, further essential work has been identified to ensure this repair can be completed safely and to the correct standard. As a result, the current stoppage will need to be extended.
During the inspection, a section of approximately 12 metres of the existing wall was found to be in significantly worse condition than originally anticipated. This section must be fully dismantled so that new foundations can be installed, before the wall can be rebuilt.
The navigation is now scheduled to reopen on 20 February 2026. These works will be completed by this date, and passage will be made available over the following weekend, ahead of the next planned stoppage at Lotmead Lock 80, which begins on 23 February 2026.
We apologise for any inconvenience this extension may cause and thank you for your patience while we complete this essential repair.
26 Jan 26 14:00:05

29585Grand Union Canal (Leicester Section - Leicestershire and Northamptonshire Union Canal)Pywells Lock No 21Pywells Lock No 2112 January 202606 March 2026We'd like to clarify the nature of the upcoming works at Pywells Lock.  The project has always been intended for gate repairs rather than a full gate replacement. The schedule remains unchanged, as other essential works are also planned during this 8-week stoppage. These repairs are crucial to maintaining the lock's safe operation until the full replacement, which is scheduled for 2035.07 Dec 25 19:55:16

29958River KennetBurghfield Lock No 103Burghfield Lock No 10317 January 202629 January 2027Further to the notice below, subsequent inspections of Lock 103 Burghfield Lock have identified that the gate is severely damaged below the waterline.

As a result, the repair is not straightforward and is likely to require dewatering of the lock.

Our Engineering and Construction teams are currently assessing feasible repair options.

We will update this notice as soon as further information becomes available, including indicative timescales for the works.

You are welcome to contact us at [enquiries.walessouthwest@canalrivertrust.org.uk](mailto:enquiries.walessouthwest@canalrivertrust.org.uk) or 03030 404040 if you would like to discuss this information with a member of our Customer Service Team.
29 Jan 26 12:00:03

29002Trent and Mersey Canal (Main Line - Middlewich to Preston Brook)Dutton Stop Lock No 76Dutton Stop Lock No 7619 January 202620 February 2026Following a recent review, we're now confident that the works can be completed within a shorter stoppage window. The revised stoppage dates are 19 January 2026 to 20 February 2026.10 Oct 25 20:11:32

29267Rochdale CanalHolmcoat Lock No 14Holmcoat Lock No 1419 January 202627 February 2026Following a recent review, we're now confident that the works can be completed within a shorter stoppage window. The revised stoppage dates are 19th January to 27th February.03 Nov 25 19:24:24

28997River KennetWoolhampton Mill Lock No 94Midgham Lock No 9219 January 202606 March 2026Please be advised that, due to overrunning works at Ham Lock and the need to move equipment between sites, the start of works at Heales Lock has been delayed.
This stoppage will now take place from 19 January to 6 March.
Thank you for your understanding and cooperation.
09 Jan 26 14:00:02

28906Leeds and Liverpool Canal (Main Line - Wigan to Leeds)Wigan Lock No 83Wigan Lock No 8319 January 202620 February 2026Following a review of the works, this stoppage has been extended until 20 February to allow for additional tasks identified on site. We will now be carrying out grouting works to both lock chambers and the upstream approach walls. Please note that the Wigan Flight will already be closed in this area, and these works will be undertaken alongside the originally planned works at other locations on the flight.28 Nov 25 12:00:05

29983Grand Union Canal (Leicester Section - Market Harborough Branch)Foxton Swing Bridge No 4Foxton Swing Bridge No 421 January 202621 January 2027Foxton Swingbridge on the Market Harborough Arm of the Grand Union Canal is currently closed due to a mechanical issue.  We are working to repair this as soon as possible and will update this notice once we have further information.21 Jan 26 19:25:00

29984Lee and Stort Navigation (River Lee)Ware Lock No 2Ware Lock No 221 January 202621 January 2027Navigation through Ware Lock is currently closed. Ware Lock is an Environment Agency's (EA) asset and was closed last week to allow the Environment Agency to carry out an inspection. During this inspection, critical safety concerns were identified with the lock gates. The Environment Agency is now awaiting a report from their contractors to confirm the extent of the works required and when navigation can safely reopen.

As the lock is owned and maintained by the Environment Agency, we are reliant on them completing their assessment and any necessary repairs before the lock can be reopened. While the lock remains closed, boats will not be able to pass through Ware Lock, and customers are advised to plan their journeys accordingly. A further update will be provided by 6 February 2026.
21 Jan 26 19:25:38

29851Oxford Canal (Southern Section - Main Line)Napton Bottom Lock No 8Greens Lock No 1426 January 202613 March 2026We'd like to clarify the winding hole locations for this stoppage. The upstream winding hole will be located above Lock 14 (Adkins Lock), and the downstream winding hole will be near Bridge 113, Folly Lane.
Please note that mooring will not be permitted within the stoppage area between Locks 8 and 14 while works are in progress.
12 Jan 26 16:00:04

29525Shropshire Union Canal (Birmingham and Liverpool Junction Canal - Main Line)Audlem Lock No 22Audlem Lock No 2226 January 202627 February 2026Following a site review of the works, we're now confident that the works can be completed within a shorter stoppage window than originally planned. The revised stoppage dates are 26th January to 27th February, meaning the whole of the Shropshire Union Canal will be open for most of January, and will be closed at Lock 10 for a shorter duration.28 Nov 25 19:32:39

29818Grand Union Canal (Grand Junction Canal - Main Line - Norton to Gayton)Buckby Lock No 12Buckby Bottom Lock No 1326 January 202606 February 2026Following an on-site review, it has been determined that the length of canal required for surveying to collect the necessary data is shorter than originally planned. The stoppage will now take place between Lock 12 and 13.08 Jan 26 19:03:02

29265Rochdale CanalCallis Lock No 13Holmcoat Lock No 1402 February 202627 February 2026Following a recent review, we're now confident that the works can be completed within a shorter stoppage window. The revised stoppage dates are 2nd February to 27th February.03 Nov 25 19:25:21

29962Grand Union Canal (Leicester Section - River Soar Navigation)Kegworth New Lock No 56Kegworth New Lock No 5602 February 202620 February 2026Kegworth New Lock 56 will be closed from 8am on 2nd February to 4pm on 20th February.

This closure is to carry out essential repairs to the bottom lock gates, improving the lock's operation following the recent replacement of the top gates ahead of the spring boating season.

Unfortunately, these works could not be completed during the original closure due to delays caused by severe weather and flooding conditions. Extending the previous stoppage at Kegworth Lock 56 would have prevented us from delivering the planned lock gate replacement at Gees Lock on the Leicester Line.
19 Jan 26 19:27:12

29186Staffordshire and Worcestershire Canal (Main Line: Stourton to Aldersley)Botterham Staircase Locks Nos 20 and 21Botterham Staircase Locks Nos 20 and 2102 February 202606 March 2026Following a review, it has been identified that the leakage at the lock is more significant than initially believed. To ensure we implement the most effective solution and secure the additional consents required, the stoppage has been rescheduled. It will now take place from 2nd February to 6th March.27 Oct 25 19:50:53

29814Grand Union Canal (Grand Junction Canal - Main Line - Gayton to Brentford)Fenny Stratford Lock No 22Soulbury Top Lock No 2602 February 202620 February 2026Due to high water levels in the area, the start of the planned stoppage has had to be rescheduled to 02/02/2026. We will be working to claw back the lost time and the end date will remain unchanged.
We apologise for the short notice of this change and thank you for your understanding.
27 Jan 26 16:00:06

29594Grand Union Canal (Grand Junction Canal - Main Line - Gayton to Brentford)Northchurch Lock No 51Northchurch Lock No 5103 February 202604 February 2026A dewatered lock head is required to replace a broken ground paddle post, this will require stop plank installation, the stoppage will start at lock 51 for water control and safety purposes.

Navigation closed, Towpath remains open.
07 Dec 25 19:56:56

29850Peak Forest Canal (Lower)Dewsnap Railway BridgeDukinfield Bridge No 209 February 202627 February 2026Following a recent survey of the sluice, we have identified that the paddle has become detached and the existing chamber stop planks have deteriorated. To safely replace these components, a stoppage is required.
While the canal is dewatered, we will also use a jet vac tanker to remove silt from in front of the sluice inlet. This will help ensure the sluice can operate effectively for flood management and continue to protect nearby critical assets.  This stoppage will run from 9 February to 27 February.
Please note that the towpath will be restricted during these works. Towpath users may be asked to wait briefly while the site is made safe for passage.
Thank you for your understanding while we carry out these essential works.
09 Jan 26 17:00:07

30043Shropshire Union Canal (Llangollen Canal - Main Line)New Marton Top Lock No 1New Marton Top Lock No 109 February 202627 February 2026We need to introduce an emergency stoppage at Lock 1, New Marton, above Welsh Frankton, on the Llangollen Canal to allow essential repair works to be carried out.
The bottom gate has developed a serious water leak, which is preventing the lock from filling correctly. Repairs are required to the lock gates and cill, along with associated brickwork restoration.
Given the impact on boats currently within the now‑isolated length of canal, we are keen to undertake these repairs now, ahead of the main boating season, to minimise longer‑term disruption.
The stoppage will be in place from 9 February until 27 February.
We apologise for any inconvenience this may cause and thank you for your understanding while we complete these vital works.
28 Jan 26 18:49:00

29595Grand Union Canal (Grand Junction Canal - Main Line - Gayton to Brentford)Berkhamsted Middle Lock No 54Berkhamsted Middle Lock No 5410 February 202611 February 2026A dewatered lock head is required to replace broken tow path Ground paddle post at lock 55, the stoppage will start at lock 54 for water control and safety purposes.

Navigation will be closed, tow path remains open
07 Dec 25 19:57:02

30025Ashby Canal (Main Line)Orton's Bridge No 1Marston Junction Bridge10 February 202611 February 2026The Engineering Team will be draining Marston Junction stop gate on the Ashby Canal to undertake a principal Inspection of the Safety Gate between Tuesday 10th February at 10am and Wednesday 11st February at 5pm.

The navigation will be closed during these times.
26 Jan 26 19:52:10

29976Birmingham Canal Navigations (Daw End Branch)Catshill Junction BridgeLongwood Bridge11 February 202614 February 2026Please be advised that navigation will be closed for four days from Wednesday 11 February between Catshill Junction and Rushall Lock 1. This stoppage is required to allow for the inspection of safety gates and the installation of a coffer dam.

Thank you for your patience while we carry out this essential maintenance. Should we be able to reopen the navigation earlier than planned, this notice will be updated accordingly.
20 Jan 26 18:40:39

30089Stourbridge Canals (Main Line)Stourbridge Lock No 2Stourbridge Lock No 216 February 202606 March 2026Essential paddle works are required at Lock 2, Stourbridge. To ensure the repairs can be carried out safely and effectively, a full navigation closure will be in place for the duration of the works. This stoppage is necessary to maintain the continued reliability and safe operation of the lock.
We understand that closures can be disruptive, and we appreciate your patience and cooperation while this essential work is completed.
02 Feb 26 19:10:54

30088River Trent (Nottingham Canal)Castle Lock No 6Castle Lock No 616 February 202627 February 2026Essential paddle works are required at Castle Lock 6. To ensure the repairs can be carried out safely and effectively, a full navigation closure will be in place for the duration of the works. This stoppage is necessary to maintain the continued reliability and safe operation of the lock.
We understand that closures can be disruptive, and we appreciate your patience and cooperation while this essential work is completed.
02 Feb 26 19:10:44

30072Coventry Canal (Main Line - Hawkesbury to Fazeley)Coleshill Road Bridge No 41Taveners Bridge No 4016 February 202608 March 2026We would like to clarify that mooring will be suspended between Bridge 41 (Coleshill Road Bridge) and Bridge 40 (Taverners Bridge) for the duration of this stoppage.
Thank you for your understanding.
30 Jan 26 16:08:51

28849Grand Union Canal (Erewash Canal)Long Eaton Lock No 61Golden Brook Aqueduct27 February 202613 March 2026A navigation and towpath closure is required to facilitate the removal of the existing footbridge, in preparation for its replacement with a modern, curving footbridge which will open up and enhance the canal and local area. This is a government-funded, local authority delivered project. We have worked closely with the local authority to reduce the impact on navigation during construction. Originally, these works were scheduled to take place over three separate stoppages. However, they can now be completed within a single two-week stoppage, supplemented by two additional navigation restrictions. These restrictions may result in boats being held for a maximum of four hours.10 Oct 25 20:11:20

30091Calder and Hebble Navigation (Main Line)Battyeford Lock No 12Battyeford Lock No 1202 March 202606 March 2026Essential paddle works are required at Battyeford Lock 17. To ensure the repairs can be completed safely and effectively, a navigation restriction will be in place for the duration of the works. These works are necessary to maintain the continued reliability and safe operation of the lock.
The navigation will remain open during this time, but boats may be asked to wait briefly while the site is made safe for passage.
Thank you for your understanding and patience.
02 Feb 26 19:11:05

29189Grand Union Canal (Warwick and Napton Canal)Welsh Road Bridge No 30Wood Lock No 1904 March 202613 March 2026Unfortunately, due to delays with the delivery of the steelwork for the HS2 viaduct, these works can no longer take place on the originally advertised dates. The stoppage is now scheduled to occur from 4th March through to 13th March.28 Oct 25 19:27:54

30090Rochdale CanalBent House Lock No 46Bent House Lock No 4606 March 202613 March 2026Essential paddle works are required at Lock 46. To ensure the repairs can be completed safely and effectively, a navigation restriction will be in place for the duration of the works. These works are necessary to maintain the continued reliability and safe operation of the lock.
The navigation will remain open during this time, but boats may be asked to wait briefly while the site is made safe for passage.
Thank you for your understanding and patience.
02 Feb 26 19:11:12

30093Leeds and Liverpool Canal (Main Line - Wigan to Leeds)Eshton Road Lock No 31Eshton Road Lock No 3109 March 202631 March 2026Essential paddle works are required at Eshton Road Lock 31. To ensure the repairs can be completed safely and effectively, a navigation restriction will be in place for the duration of the works. These works are necessary to maintain the continued reliability and safe operation of the lock. 
The navigation will remain open during this time, but boats may be asked to wait briefly while the site is made safe for passage.
Thank you for your understanding and patience.
02 Feb 26 19:11:20

IDCanalFromToStart DateEnd DateDescription ( Click to see original C&RT Notice )Last Updated

IDCanalFromToStart DateEnd DateDescription ( Click to see original C&RT Notice )Last Updated

IDCanalFromToStart DateEnd DateDescription ( Click to see original C&RT Notice )Last Updated

26514Trent and Mersey Canal (Main Line - Etruria to Hardings Wood)Harecastle Tunnel (northern entrance)Harecastle Tunnel (southern entrance)01 March 202502 May 2026Harecastle Tunnel Summer opening times from 1st March 2025 to 31st October 2025:

Open passages are available from 8am to 12 noon, Monday to Sunday. Un-booked (Open) passages must arrive at the tunnel portal between 8am and 12 noon. There is no guarantee of passage for arrivals after 12 noon unless pre-booked the day before by booking Alternatively, please contact our customer services department on 0303 0404040.


Bookable passages are available Southbound (Kidsgrove to Tunstall) at 2pm and 4pm and Northbound (Tunstall to Kidsgrove) at 1pm and 3pm.


For direct tunnel enquiries please email eventsnorthstaffs@canalrivertrust.org.uk


Please always follow the directions of our team members on site. Passage is only permitted with a working horn and tunnel light; at present we are unable to lend such items.












06 May 25 19:24:56

24824Shropshire Union Canal (Montgomery Canal - connected and navigable)Frankton Staircase Lock No 1Frankton Bottom Lock No 317 March 202502 May 2026Frankton Locks Summer Opening Times 2025:

Opening Times: 9:00 hrs - 13:00 hrs daily


Booking is required for passage through the locks and booking must be made no later than the day before passage. There will be no passage outside of these opening times.


Online booking is available, please click to Customers are advised that there is a maximum of 12 boats allowed down the locks and 12 boats allowed up the locks per day. Booking in advance is recommended to avoid disappointment.


There is a minimum of 1 night and a maximum of 14 nights stay.


If you have any questions, then please email enquiries.westmidlands@canalrivertrust.org.uk or call us on 0303 040 4040












06 May 25 19:24:52

26642Grand Union Canal (Leicester Section - Old Grand Union)Watford Bottom Lock No 1Watford Top Lock No 729 March 202502 May 2026Watford Lock Flight Opening Times:

29th March 2025:


Flight open 09:30am, last boat in at 2:45pm


30th March 2025 - 28th June 2025


Flight open 8am, last boat in at 5pm


29th June 2025 - 13th September 2025


Flight open 8am, last boat in at 6pm


14th September 2025 - 25th October 2025


Flight open 8am, last boat in at 5pm


26th October 2025 - 28th March 2026


Flight open 09.30am, last boat in at 3pm


Please ensure you have booked in with the lock keeper before you enter Lock 1 or 7.


The lock keeper will either be on the flight, or in the Top Lock Keepers Hut.


If you enter the Locks without booking in, you may be required to back out, as other boats may be working the flight.


Please follow any advice given by Trust representatives on site.












06 May 25 19:24:58

26643Grand Union Canal (Leicester Section - Old Grand Union)Foxton Bottom StaircaseFoxton Top Staircase29 March 202502 May 2026Foxton Lock Flight Opening Times:

29th March 2025:


Flight open 09:30am, last boat in at 2:45pm


30th March 2025 - 28th June 2025


Flight open 8am, last boat in at 5pm


29th June 2025 - 13th September 2025


Flight open 8am, last boat in at 6pm


14th September 2025 - 25th October 2025


Flight open 8am, last boat in at 5pm


26th October 2025 - 28th March 2026


Flight open 09.30am, last boat in at 3pm


Please ensure you have booked in with the lock keeper before you enter Lock 8 or 17.


The lock keeper will either be on the flight, or in the Top Lock Keepers Hut.


If you enter the Locks without booking in, you may be required to back out, as other boats may be working the flight.


Please follow any advice given by Trust representatives on site.












06 May 25 19:24:58

27557Lee and Stort Navigation (River Lee)Ware Lock No 2Ware Lock No 217 May 202506 November 2026If you are using Ware Lock, this unmanned structure is owned by the Environment Agency who have issued guidance to help boaters avoid getting stuck.

LOCK OPERATION – Please Follow the below guidance to operate the lock
 
For Craft going upstream towards Hertford.
1.      Open the sluices to drain the lock to low level.
2.      Open the Downstream gates
3.      Manoeuvre your craft into the basin
4.      Close the gates
5.      ENSURE that the Sluice is fully closed for both downstream gates ( see picture below)
6.      Open the upstream sluices and allow the basin to fill
7.      Close the upstream sluice
8.      Open the gates
Failure to check Point (5) may result in having to drain the basin and start again.

For Craft travelling away from Hertford
1.      Ensure that the downstream gates are closed
2.      Close the Sluices of the downstream gates (this MUST be done when the chamber is at low level)
3.      Check the Slice marker (picture above) is fully closed
4.      Open the Upstream sluices  
5.      Fill the basin
6.      Open the gates and manoeuvre the craft into the lock basin
7.      Close the Upstream sluice and gates
8.      Open the downstream sluice drain the basin
9.      Open the gates and manoeuvre the craft out of the lock
06 Nov 25 19:15:20

27824Chesterfield Canal (Norwood to Retford)Kilton Lock No 52Kilton Lock No 5211 June 202506 November 2026Kilton Lock to Bracebridge Lock – 1st October to 31st March

Assisted passage on Mondays and Thursdays will remain in place over the winter period, though this will be via a booking system.
Please contact 03030 404040 or [enquiries.yorkshirenortheast@canalrivertrust.org.uk](mailto:enquiries.yorkshirenortheast@canalrivertrust.org.uk) to make a booking.

Bookings for Mondays must be made by 3pm on Friday. Thursday bookings will be taken with no less than 48-hours notice. Passage will take place at 11am where Bracebridge and Kilton Locks will be unlocked to allow craft to pen through.
06 Nov 25 19:15:24

28944Sheffield and South Yorkshire Navigation (Stainforth and Keadby Canal)Keadby Junction LockKeadby Junction Lock01 October 202531 March 2026Keadby Lock will be available for passage during the winter period where tides are suitable between the hours of 08:00 and 16:00. To make a booking enquiry please contact the lock keeper via 07733 124611.

Please note the landline will not be monitored over winter.
10 Oct 25 20:11:27

28951Aire and Calder Navigation (Selby Section)Selby Junction LockSelby Junction Lock01 October 202531 March 2026Selby Lock – Winter Opening Hours
1st October 2025 – 31st March 2026
Selby Lock will be available for passage during the winter period, subject to suitable tides, between the hours of 08:00 and 16:00.
A minimum of 48 hours' notice is required for the lock keeper to facilitate passage.
To make a booking enquiry, please contact the lock keeper via Selby Lock. 01757 703182
10 Oct 25 20:11:28

28945Chesterfield Canal (Retford to the Trent)West Stockwith LockWest Stockwith Lock01 October 202531 March 2026West Stockwith Lock will be available for passage during the winter period where tides are suitable between the hours of 08:00 and 16:00.

To make a booking enquiry please contact the lock keeper via 07884238780.

Please note the landline will not be monitored over winter.
10 Oct 25 20:11:27

29082Leeds and Liverpool Canal (Main Line - Wigan to Leeds)Bank Newton Top Lock No 41Kirkstall Forge Staircase Locks Nos 8 to 1009 October 202519 December 2026As we move into Winter Hours, the both locks listed below must now be booked at least 72 hours in advance. This year, Newlay and Forge have been added to the winter-hours booking schedule alongside 3 & 5 Rise.
Winter hours run from Monday 1st December to Tuesday 31st March 2026.
 
3 & 5 Rise – Booking Arrangements
Up the flight
 
* Monday, Wednesday, Friday, Sunday
* Booking slots: 9:00–10:00 and 10:00–11:00
 
Down the flight
 
* Monday, Wednesday, Friday, Sunday
* Booking slots: 11:00–12:00 and 12:00–13:00
 
Please use the online booking system on our website to book passage.
Bookings must be made at least 72 hours before travel — no late bookings can be accepted.
Wide Beam Vessels:
If your boat is over 7ft wide, you must book directly with our Yorkshire & North East Customer Service Team, as wide beams require separate passage and cannot share lock space.
Call 03030 404040 (Mon–Fri, 8:00–16:30) with at least 72 hours' notice.
 


Newlay & Forge – Booking Arrangements

To book Newlay & Forge,
Please use the online booking system on our website to book passage.
Bookings must be made at least 72 hours before travel — no late bookings can be accepted.

Wide Beam Vessels:
If your boat is over 7ft wide, you must book directly with our Yorkshire & North East Customer Service Team, as wide beams require separate passage and cannot share lock space.
Call 03030 404040 (Mon–Fri, 8:00–16:30) with at least 72 hours' notice.
 
 
Available booking days and times:
  Tuesday: Down the flight from 9:00–11:00, Up the flight from 11:00–13:00
  Thursday: Down the flight from 9:00–13:00, Up the flight from 11:00–13:00
  Saturday: Down the flight from 9:00–13:00, Up the flight from 11:00–13:00
 
A minimum of 72 hours' notice is required for all winter-hours bookings.
We will review these arrangements as the season progresses.
If you need any further information, feel free to give us a call. Thanks for your help.
19 Dec 25 12:00:02

29306Trent and Mersey Canal (Main Line - Etruria to Hardings Wood)Harecastle Tunnel (northern entrance)Harecastle Tunnel (southern entrance)01 November 202528 February 2026Please note the available passage times for Harecastle Tunnel over the Christmas period are as follows:

* Monday 22nd: 9:00am – 12:00 noon
* Tuesday 23rd: Closed
* Wednesday 24th: Closed
* Thursday 25th Closed
* Friday 26th: Closed
* Saturday 27th: 9:00am – 12:00 noon
* Sunday 28th: Closed
* Monday 29th: 9:00am – 12:00 noon
* Tuesday 30th: Closed
* Wednesday 31st: Closed
* Thursday 1st: Closed
* Friday 2nd: Closed
* Saturday 3rd: 9:00am – 12:00 noon
16 Dec 25 13:00:04

30041Trent and Mersey Canal (Main Line - Etruria to Hardings Wood)Harecastle Tunnel (northern entrance)Harecastle Tunnel (northern entrance)01 March 202631 October 2026Harecastle Tunnel Summer opening times from 1 March 2026 to 31 October 2026:

All passages must be pre-booked 48hrs before passage [online]( . There is no guarantee of passage for boats unless pre-booked. 

Bookable passages are available:

* Southbound (Kidsgrove to Tunstall) at 8am, 10am, 12pm, and 2pm
* Northbound (Tunstall to Kidsgrove) at 9am, 11am, 1pm and 3pm

If you turn up earlier than your booked slot, the Tunnel Keepers will do their best to get you through. Alternatively, please contact us on 0303 0404040. For direct tunnel enquiries please email

Please always follow the directions of our team members on site. Passage is only permitted with a working horn and tunnel light; at present we are unable to lend such items.