29181Anderton LiftAnderton Lift (River Weaver)Anderton Lift (Trent and Mersey)03 January 202506 May 2027Earlier this year, the Anderton Boat Lift was closed after a lifting wire failure during planned routine maintenance by our teams. Unfortunately, it is not possible to reopen the lift using the existing gate lifting system. Trust engineers have been working closely with specialist consultants to develop a solution that will see the original rope-and-pulley mechanism replaced on all gates with a more modern, robust and safer lifting system making the lift more reliable.

We're pleased to confirm that the Trust has prioritised the funding required to support the detailed engineering design. However, this work will take time, and the lift will remain closed throughout all next year 2026. We understand how frustrating this closure will be for boaters who regularly use this vital link between the Weaver Navigation and the rest of the Trust's network. The significant investment we're making into this repair reflects how important the lift is to our waterways. Although the lift itself will stay closed, the Anderton Boat Lift Visitor Centre will remain open, with an exciting programme of events and activities planned for 2026. We hope you'll continue to visit and enjoy everything the site has to offer.

This essential redesign work is being delivered ahead of, and separately from, the wider refurbishment programme. We'll continue to share updates as the project progresses.

We also understand the impact that Marsh Lock's closure is having on customers wanting to visit the Weaver. Our teams are working through the options to bring the lock back into operation, and you can follow updates [here.](

Thank you for your ongoing patience and support for this vital and historic structure.
06 May 26 18:43:32

IDCanalFromToStart DateEnd DateDescription ( Click to see original C&RT Notice )Last Updated

31312Huddersfield Narrow CanalShaker Wood Lock No 25EShaker Wood Lock No 25E03 June 202603 June 2027We have had to place a navigation closure on the Huddersfield Narrow Canal at Lock 25E as the head paddles had been left up, draining the pound. So a closure is in place until the water levels in the pound have recovered. We will closely monitor the water levels and will update and reopen the lock when it is ready for operation.03 June 26 18:55:42

31255Huddersfield Narrow CanalStanley Dawson Lock No 1EBooth Lock No 31E15 June 202629 May 2027Works taking place at Slaithwaite Reservoir have necessitated a drawdown of reservoir levels that has been ongoing for several months. With recent warm, dry weather and an increase in boat movement on the canal, we have insufficient water resources to maintain navigation for the long term on the lower section of the canal.
 
From Monday 15th June 2026 navigation between Lock 1E and Lock 31E will close with these locks being padlocked closed.
 
Whilst the closure is in effect passage will only be possible between Standedge Tunnel and Lock 31E. Anyone looking to transit through Standedge Tunnel from Diggle in the Northwest will only be permitted to do so with a return tunnel booking. Boats will be able to turn in the winding hole above Lock 31E.
 
Should levels in Slaithwaite Reservoir improve enough to provide an opportunity to open a passage window then details of this will be communicated by way of an update to this notice. 
29 May 26 18:08:14

IDCanalFromToStart DateEnd DateDescription ( Click to see original C&RT Notice )Last Updated

30524Leeds and Liverpool Canal (Stanley Dock Branch)Stanley Bottom Lock No 4Mann Island Basin15 May 202605 July 2026The Liverpool Link will be temporarily closed from 15 May to 5 July while Peel carries out essential construction and maintenance works in the Central Docks.

We have worked to keep disruption to a minimum; however, as our rights are limited to permitting our customers to travel through Peel's property, the owners are able to close this section at any time to carry out necessary repairs and maintenance. The Trust has very limited control over access to this area and has not been able to prevent this closure.

During this time, access to Albert Dock and Salthouse Dock will only be possible via Brunswick Lock, which can be booked directly through Liverpool Marina. This route requires a crossing from Ellesmere Port via the Manchester Ship Canal and the River Mersey.

We understand this may affect your plans, and we're working closely with Peel to keep disruption to a minimum. If you already have a booking during the closure period, our team will have been in contact to talk through any changes and help make alternative arrangements where needed.
Outside of these dates, Liverpool Link passages and moorings into Salthouse Dock will continue as normal.

If you'd like to make a new booking or discuss an existing one, our North West Customer Service Team will be happy to help on 0303 0404 040.
We are sorry for any disruption caused to your boating plans during this closure.
06 April 26 12:54:31

IDCanalFromToStart DateEnd DateDescription ( Click to see original C&RT Notice )Last Updated

19378Middle Level Navigations (Forty Foot River)Welches Dam SluiceWelches Dam Sluice13 October 202312 October 2099This lock is closed permanently.13 October 23 19:19:13

IDCanalFromToStart DateEnd DateDescription ( Click to see original C&RT Notice )Last Updated

31250River Avon - Warwickshire (Lower Avon Navigation)Nafford LockNafford Lock13 April 202604 July 2026The Trust identified that Nafford Lock would not survive another season and therefore would require a full dewater and refurbishment. This assessment has been proved to be correct.

The Trust closed the lock on Monday 13th April 2026. As soon as we could following the winter floods.

From our records the last time that this lock was dewatered was in 1985 (41 years ago).
29 May 26 18:02:14

IDCanalFromToStart DateEnd DateDescription ( Click to see original C&RT Notice )Last Updated

30807River KennetGarston Lock No 102Sheffield Lock No 10101 June 202601 June 2027Further to the notice below, we would like to advise customers that Garston Lock is open, however please note that it currently takes 15 minutes to refill.

Further repair works are scheduled to begin during the W/C 8th June.

We will provide additional details and timings later this week as they become available.

You are welcome to contact us at [enquiries.walessouthwest@canalrivertrust.org.uk](mailto:enquiries.walessouthwest@canalrivertrust.org.uk) or 03030 404040 if you would like to discuss this information with a member of our Customer Service Team.
01 June 26 16:00:05

31038River KennetBurghfield Lock No 103Garston Lock No 10201 June 202601 June 2027Further to the notice below, we are pleased to confirm that repair works at Burghfield Lock have now been completed and the lock is now open.
 
Garston Lock is also open however, please note that it currently takes approximately 15 minutes to fill.

Further repair works are scheduled to begin at Garston Lock during the week commencing 8th June.

We will provide additional details and timings later this week as they become available.

You are welcome to contact us at [enquiries.walessouthwest@canalrivertrust.org.uk](mailto:enquiries.walessouthwest@canalrivertrust.org.uk) or 03030 404040 if you would like to discuss this information with a member of our Customer Service Team.
01 June 26 12:00:02

30911River KennetHeals Lock No 93Heals Lock No 9305 October 202620 November 2026We apologise for the need to schedule an in‑season stoppage on the Kennet & Avon Canal.

We are carrying out essential improvement works at Heales Lock 93, including the replacement of the top and bottom gates.

To complete this work safely, a stoppage will be in place from 5th October until the 20th November.

These works were originally planned for the recent intensive maintenance period but had to be deferred due to flooding and river conditions preventing mobilisation to site.

Following local consultation it has been agreed that this is the preferred time to undertake these essential works.

Thank you for your understanding and patience while these improvements take place.

You are welcome to contact us at [enquiries.walessouthwest@canalrivertrust.org.uk](mailto:enquiries.walessouthwest@canalrivertrust.org.uk) or 03030 404040 if you would like to discuss this information with a member of our Customer Service Team.
06 May 26 18:43:48

IDCanalFromToStart DateEnd DateDescription ( Click to see original C&RT Notice )Last Updated

30698Rochdale CanalButler Lane Lock No 81Ancoats Lower Lock No 8331 March 202603 June 2027We are currently in discussions with the neighbouring landowner to secure the necessary access to their land, which is required to undertake repairs to the canal wash wall and canal bed,
A start date for the repair works will be confirmed once access arrangements have been agreed.
A further update will be provided on or before Friday, 12 June.
03 June 26 12:00:02

31048Rochdale Canal (Main Line)Little Clegg Swing Bridge No 54ALittle Clegg Swing Bridge No 54A07 May 202605 June 2027Navigation remains closed at Little Clegg Swing Bridge on the Rochdale Canal due to a fault with the lock mechanism and the hydraulic hose that operates the swing bridge.

Our contractors have undertaken initial repair works, however, additional parts are required to complete the repair. Once these parts have arrived, contractors will return to site to carry out the essential works and restore normal operation as quickly as possible.

In the meantime, assisted passages will be available to help customers navigate through Little Clegg Swing Bridge.

Assisted passages are available at the following times:

Monday to Friday: 8:30am – 2:00pm

Saturday and Sunday: 12:30pm

If you wish to pass through the affected area, please contact our North West Customer Support Team on 0303 040 4040 with at least 48 hours' notice during the following opening hours:

Monday to Thursday: 8:30am – 5:00pm

Friday: 8:30am – 4:30pm

A further update will be provided on Wednesday, 10 June.
05 June 26 13:00:06

31258Rochdale Canal (Main Line)Sowerby Bridge Lock No 1Tuel Lane Lock No 329 May 202605 June 2027The works to the neighbouring property, to prevent damage from canal water, are progressing well and we are still on track to raise water levels to normal on Wednesday 10th June 2026 to test the effectiveness of the repair.
 
Subject to the repairs proving successful, passage will be available from Friday 12th June and operation of Tuel Lock will following this pattern: -
 
Mondays and Fridays 0800-1600 no prior booking required
Sundays 1000-1500 no prior booking required
 
We will confirm the effectiveness of the repair, and whether we are in the position to offer passage by 5pm on Wednesday 10th June 2026.
05 June 26 16:00:06

IDCanalFromToStart DateEnd DateDescription ( Click to see original C&RT Notice )Last Updated

30698Rochdale CanalButler Lane Lock No 81Ancoats Lower Lock No 8331 March 202603 June 2027We are currently in discussions with the neighbouring landowner to secure the necessary access to their land, which is required to undertake repairs to the canal wash wall and canal bed,
A start date for the repair works will be confirmed once access arrangements have been agreed.
A further update will be provided on or before Friday, 12 June.
03 June 26 12:00:02

31048Rochdale Canal (Main Line)Little Clegg Swing Bridge No 54ALittle Clegg Swing Bridge No 54A07 May 202605 June 2027Navigation remains closed at Little Clegg Swing Bridge on the Rochdale Canal due to a fault with the lock mechanism and the hydraulic hose that operates the swing bridge.

Our contractors have undertaken initial repair works, however, additional parts are required to complete the repair. Once these parts have arrived, contractors will return to site to carry out the essential works and restore normal operation as quickly as possible.

In the meantime, assisted passages will be available to help customers navigate through Little Clegg Swing Bridge.

Assisted passages are available at the following times:

Monday to Friday: 8:30am – 2:00pm

Saturday and Sunday: 12:30pm

If you wish to pass through the affected area, please contact our North West Customer Support Team on 0303 040 4040 with at least 48 hours' notice during the following opening hours:

Monday to Thursday: 8:30am – 5:00pm

Friday: 8:30am – 4:30pm

A further update will be provided on Wednesday, 10 June.
05 June 26 13:00:06

31258Rochdale Canal (Main Line)Sowerby Bridge Lock No 1Tuel Lane Lock No 329 May 202605 June 2027The works to the neighbouring property, to prevent damage from canal water, are progressing well and we are still on track to raise water levels to normal on Wednesday 10th June 2026 to test the effectiveness of the repair.
 
Subject to the repairs proving successful, passage will be available from Friday 12th June and operation of Tuel Lock will following this pattern: -
 
Mondays and Fridays 0800-1600 no prior booking required
Sundays 1000-1500 no prior booking required
 
We will confirm the effectiveness of the repair, and whether we are in the position to offer passage by 5pm on Wednesday 10th June 2026.
05 June 26 16:00:06

IDCanalFromToStart DateEnd DateDescription ( Click to see original C&RT Notice )Last Updated

30767Worcester and Birmingham Canal (Diglis Junction to Diglis Basin)Diglis Lock No 2Blockhouse Lock No 407 April 202605 June 2027Following our previous update, specialist divers have now begun installation works. However, progress is taking longer than anticipated and, to ensure diver safety, further restrictions will be in place from Monday 8 June to Wednesday 10 June.

Once the screens are installed, a period of pump system testing will also be required. This will involve controlled use of water within the basin and will necessitate additional restrictions.

Navigation between Diglis Lock and the River Severn will be temporarily restricted as follows:

Saturday 6th June - Sunday 7th June

* Morning booked passage at 11am
* Afternoon booked passage at 2pm.

Monday 8th June - Wednesday 10th June

* Morning booked passage at 7am
* Afternoon booked passage at 4pm.
* The River Severn pontoon will be closed during these works.

Thursday 11th June - Friday 12th June

* Morning booked passage at 9am.
* Afternoon booked passage at 2pm.

As previously, all passages are subject to sufficient water levels being available in the basin. Please note a maximum of three 'lockages' will be available for each slot (up to six boats per direction).

To book a passage through Diglis Lock 1 (River Lock), please contact:

* 0303 040 4040
* enquiries.westmidlands@canalrivertrust.org.uk.

Out of office hours please ask to be forwarded to the Duty Manager.

We apologise for the inconvenience this essential work may cause and appreciate your patience.
05 June 26 10:00:01

IDCanalFromToStart DateEnd DateDescription ( Click to see original C&RT Notice )Last Updated

30122Trent and Mersey Canal (Main Line - Etruria to Hardings Wood)Harecastle Tunnel (northern entrance)Harecastle Tunnel (southern entrance)01 March 202631 October 2026Following feedback on our original operating proposal, the Trust have revised the booking arrangements for Harecastle Tunnel.

From 1 April 2026, passages will operate as follows:

* Bookable passages at 8am (Southbound) and 9am (Northbound)
* Open, non bookable window from 10am to 2pm
* Bookable passages at 2pm (Southbound) and 3pm (Northbound)

The open window allows boats to arrive and pass through without a booking, subject to capacity and safe operation on the day. Each passage can accommodate up to eight boats.

While these times provide a clear structure, the tunnel team will remain flexible wherever possible. Staff and volunteers will use their judgement on the day to make best use of available capacity, including accommodating unbooked boats, using unused booking slots, or allowing early arrivals to join an earlier passage where it is safe to do so.

Changes to bookings should be made by 5pm on the day before your planned passage wherever possible. Where late changes cannot be made online, the team will try to accommodate them on the day, although this cannot be guaranteed.

Please pre-book online here: < >. For any other enquiries, please contact us on 0303 0404040. For direct tunnel enquiries please email eventsnorthstaffs@canalrivertrust.org.uk.
06 April 26 12:54:27

IDCanalFromToStart DateEnd DateDescription ( Click to see original C&RT Notice )Last Updated

19378Middle Level Navigations (Forty Foot River)Welches Dam SluiceWelches Dam Sluice13 October 202312 October 2099This lock is closed permanently.13 Oct 23 19:19:13

25756Bridgewater Canal (Main Line)Agden Bridge No 26Dunham Town Bridge No 2702 January 202506 May 2027The Bridgewater Canal is currently closed between Agden Bridge No. 26 and Dunham Town Bridge No. 27 due to a breach. This section is managed by the Bridgewater Canal Company, not the Canal & River Trust. However, as this canal connects to our network and forms part of the Cheshire Cruising Ring, we are liaising closely with them.

Nearest Winding Holes:

* West of the Breach: Between Oughtrington Bridge No. 24 and Lymm Bridge No. 23.
* East of the Breach: Between Seamon's Moss Bridge No. 29 and Broadheath Bridge No. 30.

Canal & River Trust Customers

If any of our customers are stuck on the Bridgewater Canal, please contact our North West Customer Service Team at 0303 0404 040 for support.

Further updates will be provided as more information becomes available. For additional details, visit the Bridgewater Canal Company website: < >
06 May 26 18:43:30

29181Anderton LiftAnderton Lift (River Weaver)Anderton Lift (Trent and Mersey)03 January 202506 May 2027Earlier this year, the Anderton Boat Lift was closed after a lifting wire failure during planned routine maintenance by our teams. Unfortunately, it is not possible to reopen the lift using the existing gate lifting system. Trust engineers have been working closely with specialist consultants to develop a solution that will see the original rope-and-pulley mechanism replaced on all gates with a more modern, robust and safer lifting system making the lift more reliable.

We're pleased to confirm that the Trust has prioritised the funding required to support the detailed engineering design. However, this work will take time, and the lift will remain closed throughout all next year 2026. We understand how frustrating this closure will be for boaters who regularly use this vital link between the Weaver Navigation and the rest of the Trust's network. The significant investment we're making into this repair reflects how important the lift is to our waterways. Although the lift itself will stay closed, the Anderton Boat Lift Visitor Centre will remain open, with an exciting programme of events and activities planned for 2026. We hope you'll continue to visit and enjoy everything the site has to offer.

This essential redesign work is being delivered ahead of, and separately from, the wider refurbishment programme. We'll continue to share updates as the project progresses.

We also understand the impact that Marsh Lock's closure is having on customers wanting to visit the Weaver. Our teams are working through the options to bring the lock back into operation, and you can follow updates [here.](

Thank you for your ongoing patience and support for this vital and historic structure.
06 May 26 18:43:32

28898River Avon (Kennet and Avon Navigation)Kelston Lock No 5Kelston Lock No 510 September 202510 October 2026Further to the notice below, please be advised that our assisted passage days at Lock 5, Kelston Lock have now finished.
However our team will be happy to support passage through the lock when we have colleagues and volunteers available.    

If you require assistance through the lock please contact us at enquiries.walessouthwest@canalrivertrust.org.uk or 03030 404040 where our team will be able to help with dates and timings.
10 Oct 25 20:11:23

29735Shropshire Union Canal (Llangollen Canal - Main Line)Grindley Brook Bottom Lock No 14Whitchurch Ring Road Bridge No 31A22 December 202504 June 2027Just to remind boaters, the closure includes Grindley Brook Locks 1 to 6.

The downstream winding hole is Thomason's Winding Hole, located near Bridge 22 (Thomason's Bridge).
04 Jun 26 10:00:02

29984Lee and Stort Navigation (River Lee)Ware Lock No 2Ware Lock No 221 January 202628 May 2027The Environment Agency is currently testing the lock gates for safe operation at Ware (No2 lock)

The lock will remain closed until there is engineering assurance around safe operation.
 
If and when it is safe, the Environment Agency will be able to advise boaters directly, However this may be limited and controlled opening.

We advise contacting the Environment Agency contact e-mail address at [hnl-aptenquiries@environment-agency.gov.uk](mailto:hnl-aptenquiries@environment-agency.gov.uk) so that you can receive information and updates regarding the lock situation.
28 May 26 15:00:06

30167Birmingham Canal Navigations (Daw End Branch)Northywood BridgeAldridge Wharf Bridge09 February 202628 May 2027We kindly remind boaters to follow the signage in place at the site. In particular:

* Boaters must pass the site at tickover speed only.
* Boats should pass as close to the offside as possible to minimise bow waves and prevent the bunds from being pulled away from the waterway wall.
28 May 26 15:00:06

30698Rochdale CanalButler Lane Lock No 81Ancoats Lower Lock No 8331 March 202603 June 2027We are currently in discussions with the neighbouring landowner to secure the necessary access to their land, which is required to undertake repairs to the canal wash wall and canal bed,
A start date for the repair works will be confirmed once access arrangements have been agreed.
A further update will be provided on or before Friday, 12 June.
03 Jun 26 12:00:02

30767Worcester and Birmingham Canal (Diglis Junction to Diglis Basin)Diglis Lock No 2Blockhouse Lock No 407 April 202605 June 2027Following our previous update, specialist divers have now begun installation works. However, progress is taking longer than anticipated and, to ensure diver safety, further restrictions will be in place from Monday 8 June to Wednesday 10 June.

Once the screens are installed, a period of pump system testing will also be required. This will involve controlled use of water within the basin and will necessitate additional restrictions.

Navigation between Diglis Lock and the River Severn will be temporarily restricted as follows:

Saturday 6th June - Sunday 7th June

* Morning booked passage at 11am
* Afternoon booked passage at 2pm.

Monday 8th June - Wednesday 10th June

* Morning booked passage at 7am
* Afternoon booked passage at 4pm.
* The River Severn pontoon will be closed during these works.

Thursday 11th June - Friday 12th June

* Morning booked passage at 9am.
* Afternoon booked passage at 2pm.

As previously, all passages are subject to sufficient water levels being available in the basin. Please note a maximum of three 'lockages' will be available for each slot (up to six boats per direction).

To book a passage through Diglis Lock 1 (River Lock), please contact:

* 0303 040 4040
* enquiries.westmidlands@canalrivertrust.org.uk.

Out of office hours please ask to be forwarded to the Duty Manager.

We apologise for the inconvenience this essential work may cause and appreciate your patience.
05 Jun 26 10:00:01

31250River Avon - Warwickshire (Lower Avon Navigation)Nafford LockNafford Lock13 April 202604 July 2026The Trust identified that Nafford Lock would not survive another season and therefore would require a full dewater and refurbishment. This assessment has been proved to be correct.

The Trust closed the lock on Monday 13th April 2026. As soon as we could following the winter floods.

From our records the last time that this lock was dewatered was in 1985 (41 years ago).
29 May 26 18:02:14

30901Leeds and Liverpool Canal (Liverpool Link)Regent Road Bascule Bridge No BBMann Island Basin23 April 202606 May 2027A suspected bloom of blue‑green algae has been identified in Princes Dock. In order to prevent the algae from entering the South Docks, the Trust must take precautionary measures. As a result, the Liverpool Link will be closed to navigation while the situation is assessed and we work with the dock owner, Peel, to prevent any further spread.
 
Boaters wishing to travel to Salthouse Dock or Albert Dock may still do so via alternative access by entering the docks from the River Mersey. If you require further information or guidance when planning your passage, please contact our North West Customer Service team on 0303 040 4040, who will be happy to assist.
 
Blue‑green algae can be very harmful further information and guidance is available [here](
06 May 26 18:43:46

31048Rochdale Canal (Main Line)Little Clegg Swing Bridge No 54ALittle Clegg Swing Bridge No 54A07 May 202605 June 2027Navigation remains closed at Little Clegg Swing Bridge on the Rochdale Canal due to a fault with the lock mechanism and the hydraulic hose that operates the swing bridge.

Our contractors have undertaken initial repair works, however, additional parts are required to complete the repair. Once these parts have arrived, contractors will return to site to carry out the essential works and restore normal operation as quickly as possible.

In the meantime, assisted passages will be available to help customers navigate through Little Clegg Swing Bridge.

Assisted passages are available at the following times:

Monday to Friday: 8:30am – 2:00pm

Saturday and Sunday: 12:30pm

If you wish to pass through the affected area, please contact our North West Customer Support Team on 0303 040 4040 with at least 48 hours' notice during the following opening hours:

Monday to Thursday: 8:30am – 5:00pm

Friday: 8:30am – 4:30pm

A further update will be provided on Wednesday, 10 June.
05 Jun 26 13:00:06

30524Leeds and Liverpool Canal (Stanley Dock Branch)Stanley Bottom Lock No 4Mann Island Basin15 May 202605 July 2026The Liverpool Link will be temporarily closed from 15 May to 5 July while Peel carries out essential construction and maintenance works in the Central Docks.

We have worked to keep disruption to a minimum; however, as our rights are limited to permitting our customers to travel through Peel's property, the owners are able to close this section at any time to carry out necessary repairs and maintenance. The Trust has very limited control over access to this area and has not been able to prevent this closure.

During this time, access to Albert Dock and Salthouse Dock will only be possible via Brunswick Lock, which can be booked directly through Liverpool Marina. This route requires a crossing from Ellesmere Port via the Manchester Ship Canal and the River Mersey.

We understand this may affect your plans, and we're working closely with Peel to keep disruption to a minimum. If you already have a booking during the closure period, our team will have been in contact to talk through any changes and help make alternative arrangements where needed.
Outside of these dates, Liverpool Link passages and moorings into Salthouse Dock will continue as normal.

If you'd like to make a new booking or discuss an existing one, our North West Customer Service Team will be happy to help on 0303 0404 040.
We are sorry for any disruption caused to your boating plans during this closure.
06 Apr 26 12:54:31

31135Macclesfield CanalBosley Top Lock No 1Bosley Top Lock No 116 May 202605 June 2027Our contractors are currently carrying out the repairs to the damaged tailgates at Lock 12 and are aiming to complete the work over the weekend.

The scaffolding is expected to be removed by 4:00 pm on Tuesday, 9 June, after which we hope to reopen the lock.

We appreciate your patience and understanding while these important works are completed.

A further update will be provided on or before Tuesday 9 June.
05 Jun 26 10:00:06

31044Sheffield and South Yorkshire Navigation (Stainforth and Keadby Canal)Keadby Junction LockKeadby Junction Lock20 May 202605 June 2027We continue to seek an effective repair methodology to seal the abandoned culvert and will offer a further update on Friday 12th June 2026.05 Jun 26 09:00:01

31217Birmingham Canal Navigations (Walsall Junction Canal)Walsall Bottom LockWalsall Top Lock27 May 202601 June 2027Please be advised that navigation on the Walsall Lock Flight remains closed.

Repair plans are currently being developed following the damage to Lock 7, and the navigation will need to remain closed while these are finalised.

We will provide a further update once a confirmed repair plan and timescales are in place.
01 Jun 26 15:00:02

31258Rochdale Canal (Main Line)Sowerby Bridge Lock No 1Tuel Lane Lock No 329 May 202605 June 2027The works to the neighbouring property, to prevent damage from canal water, are progressing well and we are still on track to raise water levels to normal on Wednesday 10th June 2026 to test the effectiveness of the repair.
 
Subject to the repairs proving successful, passage will be available from Friday 12th June and operation of Tuel Lock will following this pattern: -
 
Mondays and Fridays 0800-1600 no prior booking required
Sundays 1000-1500 no prior booking required
 
We will confirm the effectiveness of the repair, and whether we are in the position to offer passage by 5pm on Wednesday 10th June 2026.
05 Jun 26 16:00:06

31271Kennet and Avon Canal (Main Line)Semington Bottom Lock No 15Bradford on Avon Lock No 1431 May 202631 May 2027Following the previous notice, water levels between Lock 14 (Bradford-on-Avon Lock) and Lock 15 (Semington Lock) have begun to recover. We aim to reopen Lock 14 at 8:00 am on Monday, 1st June, with lock keepers on-site to assist.
We anticipate a backlog of boats and ask for your patience as the team assists customers through.
Please note that water levels will be monitored throughout the day, so lock operating hours may be subject to change if required.
31 May 26 21:00:01

31038River KennetBurghfield Lock No 103Garston Lock No 10201 June 202601 June 2027Further to the notice below, we are pleased to confirm that repair works at Burghfield Lock have now been completed and the lock is now open.
 
Garston Lock is also open however, please note that it currently takes approximately 15 minutes to fill.

Further repair works are scheduled to begin at Garston Lock during the week commencing 8th June.

We will provide additional details and timings later this week as they become available.

You are welcome to contact us at [enquiries.walessouthwest@canalrivertrust.org.uk](mailto:enquiries.walessouthwest@canalrivertrust.org.uk) or 03030 404040 if you would like to discuss this information with a member of our Customer Service Team.
01 Jun 26 12:00:02

30807River KennetGarston Lock No 102Sheffield Lock No 10101 June 202601 June 2027Further to the notice below, we would like to advise customers that Garston Lock is open, however please note that it currently takes 15 minutes to refill.

Further repair works are scheduled to begin during the W/C 8th June.

We will provide additional details and timings later this week as they become available.

You are welcome to contact us at [enquiries.walessouthwest@canalrivertrust.org.uk](mailto:enquiries.walessouthwest@canalrivertrust.org.uk) or 03030 404040 if you would like to discuss this information with a member of our Customer Service Team.
01 Jun 26 16:00:05

31290Birmingham Canal Navigations (Rushall Canal)Rushall Flight Top Lock No 1Rushall Flight Bottom Lock No 901 June 202605 June 2027Please be advised that the Rushall Lock Flight remains closed as levels are still not sufficient to safely reopen the flight at this time.

Our teams will continue to closely monitor the situation and manage levels as far as possible. We will provide a further update on Monday.
05 Jun 26 15:00:04

31312Huddersfield Narrow CanalShaker Wood Lock No 25EShaker Wood Lock No 25E03 June 202603 June 2027We have had to place a navigation closure on the Huddersfield Narrow Canal at Lock 25E as the head paddles had been left up, draining the pound. So a closure is in place until the water levels in the pound have recovered. We will closely monitor the water levels and will update and reopen the lock when it is ready for operation.03 Jun 26 18:55:42

31159Grand Union Canal (Grand Junction Canal - Main Line - Gayton to Brentford)Boxmoor Bottom Lock No 64Boxmoor Bottom Lock No 6409 June 202610 June 2026Our Asset team have identified two damaged ground paddle posts at lock 64, this is restricting normal use of the lock for navigation.

A dewatered lock head with top stop plank installation is required to carryout replacement of both Tow Path and Off side ground paddle posts.

While the lock head is dewatered we will also service and repair as required all gate & ground paddle connections rods & brackets and inspect the lock paddle culverts for defects.
20 May 26 17:38:11

31320Staffordshire and Worcestershire Canal (Main Line: Stourton to Aldersley)Wightwick Mill Lock No 30Wightwick Mill Lock No 3010 June 202610 June 2026Please be advised that there will be a navigation closure in place while we carry out repairs to a broken paddle stand at Wightwick Mill Lock, in Wolverhampton.

We thank you for your patience and apologise for any inconvenience that this may cause.
03 Jun 26 18:57:22

31255Huddersfield Narrow CanalStanley Dawson Lock No 1EBooth Lock No 31E15 June 202629 May 2027Works taking place at Slaithwaite Reservoir have necessitated a drawdown of reservoir levels that has been ongoing for several months. With recent warm, dry weather and an increase in boat movement on the canal, we have insufficient water resources to maintain navigation for the long term on the lower section of the canal.
 
From Monday 15th June 2026 navigation between Lock 1E and Lock 31E will close with these locks being padlocked closed.
 
Whilst the closure is in effect passage will only be possible between Standedge Tunnel and Lock 31E. Anyone looking to transit through Standedge Tunnel from Diggle in the Northwest will only be permitted to do so with a return tunnel booking. Boats will be able to turn in the winding hole above Lock 31E.
 
Should levels in Slaithwaite Reservoir improve enough to provide an opportunity to open a passage window then details of this will be communicated by way of an update to this notice. 
29 May 26 18:08:14

30914Gloucester and Sharpness CanalGloucester Dock LockGloucester Dock Lock29 June 202610 July 2026Please be advised that essential maintenance works are required at Gloucester Lock 2, including the re‑installation of stop plank channels, repairs to the west dockside ground paddle, and associated surveys within the lock.

These works were originally planned for November 2025 but could not proceed due to insufficient water depths across the dock, which prevented safe access.

The works were later provisionally rescheduled for the post‑Christmas stoppage period but were again unable to proceed due to river flood conditions, preventing safe access and working at the river entrance to the lock.

A revised planned closure is now scheduled from 29th June to 10th July 2026.

During this period, Gloucester Lock 2 and its approaches will be closed between 09:00 and 16:00 on weekdays.

Passage through the lock will be available outside of these hours, including during the weekend within the stoppage.

We apologise for any inconvenience caused and thank customers for their patience and understanding.

You are welcome to contact us at [enquiries.walessouthwest@canalrivertrust.org.uk](mailto:enquiries.walessouthwest@canalrivertrust.org.uk) or 03030 404040 if you would like to discuss this information with a member of our Customer Service Team
06 May 26 18:43:49

30733Staffordshire and Worcestershire Canal (Stourport Basins: Broad Route)Stourport Lower Broad LockStourport Lower Broad Lock07 September 202619 October 2026We apologise for the need to schedule an in‑season stoppage on the Staffordshire & Worcestershire Canal.
 
We're carrying out essential improvement works at Bottom Barge Lock, including the replacement of the top gates and coping stone repairs. To complete this work safely, a stoppage will be in place from 7 September to 19 October 2026
 
These works were originally planned for the recent Intensive Maintenance Period but had to be deferred. During our final preparations, we identified on‑site conditions that meant the works could not be carried out safely or without causing disruption to moored craft at that time. Following local consultation, it has been agreed that this is the preferred time to undertake these essential works.
 
During the stoppage, the narrow lock between the Severn and the canal will remain open, and boats up to 2.1 metres in width will still be able to move between the basin and the river. Only wider craft will be restricted from passing through the site during this period.
 
We appreciate your understanding and patience while these improvements take place.
06 Apr 26 12:54:36

30911River KennetHeals Lock No 93Heals Lock No 9305 October 202620 November 2026We apologise for the need to schedule an in‑season stoppage on the Kennet & Avon Canal.

We are carrying out essential improvement works at Heales Lock 93, including the replacement of the top and bottom gates.

To complete this work safely, a stoppage will be in place from 5th October until the 20th November.

These works were originally planned for the recent intensive maintenance period but had to be deferred due to flooding and river conditions preventing mobilisation to site.

Following local consultation it has been agreed that this is the preferred time to undertake these essential works.

Thank you for your understanding and patience while these improvements take place.

You are welcome to contact us at [enquiries.walessouthwest@canalrivertrust.org.uk](mailto:enquiries.walessouthwest@canalrivertrust.org.uk) or 03030 404040 if you would like to discuss this information with a member of our Customer Service Team.
06 May 26 18:43:48

IDCanalFromToStart DateEnd DateDescription ( Click to see original C&RT Notice )Last Updated

IDCanalFromToStart DateEnd DateDescription ( Click to see original C&RT Notice )Last Updated

IDCanalFromToStart DateEnd DateDescription ( Click to see original C&RT Notice )Last Updated

27824Chesterfield Canal (Norwood to Retford)Kilton Lock No 52Kilton Lock No 5211 June 202506 May 2027Kilton Lock to Bracebridge Lock - 1st April 2026 to 30th September 2026
From 1st April 2026, booking will no longer be needed. The Operative Team will be present at the lock on Monday and Thursday every week at 11am for passage through the locks. Please ensure crafts are at the locks for these times for staff to know who is wishing to have passage.

Passage will be conducted one way at a time, it may be a short time after 11am that assistance reaches you if those travelling the other direction are going first.
06 May 26 18:43:31

30122Trent and Mersey Canal (Main Line - Etruria to Hardings Wood)Harecastle Tunnel (northern entrance)Harecastle Tunnel (southern entrance)01 March 202631 October 2026Following feedback on our original operating proposal, the Trust have revised the booking arrangements for Harecastle Tunnel.

From 1 April 2026, passages will operate as follows:

* Bookable passages at 8am (Southbound) and 9am (Northbound)
* Open, non bookable window from 10am to 2pm
* Bookable passages at 2pm (Southbound) and 3pm (Northbound)

The open window allows boats to arrive and pass through without a booking, subject to capacity and safe operation on the day. Each passage can accommodate up to eight boats.

While these times provide a clear structure, the tunnel team will remain flexible wherever possible. Staff and volunteers will use their judgement on the day to make best use of available capacity, including accommodating unbooked boats, using unused booking slots, or allowing early arrivals to join an earlier passage where it is safe to do so.

Changes to bookings should be made by 5pm on the day before your planned passage wherever possible. Where late changes cannot be made online, the team will try to accommodate them on the day, although this cannot be guaranteed.

Please pre-book online here: < >. For any other enquiries, please contact us on 0303 0404040. For direct tunnel enquiries please email eventsnorthstaffs@canalrivertrust.org.uk.
06 Apr 26 12:54:27

30632Leeds and Liverpool Canal (Main Line - Wigan to Leeds)Five Rise Locks Swing Bridge No 200Kirkstall Forge Staircase Locks Nos 8 to 1031 March 202615 May 2027Please be advised that, with immediate effect, opening times at Gargrave and Bank Newton Locks have changed.
The locks will now operate from 10:00am to 4:00pm daily, replacing the previous opening time of 8:00am.
This change is being introduced to ensure our operational team has sufficient time to travel between and attend all locations safely and efficiently.
Please note all other timings for locks remain the same
We appreciate your understanding and cooperation.
15 May 26 09:00:04

30830Shropshire Union Canal (Montgomery Canal - connected and navigable)Frankton Top LockFrankton Bottom Lock No 301 April 202630 October 2026Frankton Locks – Summer Opening Times 2026

Opening hours:

* 09:00–13:00 daily

All passages through Frankton Locks are by advance booking only. Bookings must be made no later than the day before passage. No passages will be permitted outside of these opening hours.

A maximum of 12 boats travelling down and 12 boats travelling up the locks is permitted each day. Customers are therefore advised to book in advance to avoid disappointment. There is a minimum stay of 1 night and a maximum stay of 14 nights on the Montgomery Canal. Please note that a return passage must be included at the time of booking.

Please book online [here]( .
06 May 26 18:43:45

31291Birmingham Canal Navigations (Main Line)Wolverhampton Bottom Lock No 21Wolverhampton Top Lock No 101 June 202605 June 2027Please be advised that navigation through the Wolverhampton Lock Flight remains restricted. Passage remains between 9am and 2pm.

Our teams will continue to closely monitor the situation and manage levels as far as possible. We will provide a further update on Monday.
05 Jun 26 15:00:05

31297Pocklington Canal (Navigable Section)Cottingwith Lock No 1Cottingwith Lock No 102 June 202602 June 2027Pocklington Canal – Booking Passage
To help us care for the Pocklington Canal and manage water levels throughout the year, we're introducing a booked passage system.
If you're planning a journey along the canal, we'd love to help — just let us know at least 48 hours in advance so we can make the necessary arrangements.
Passages are available Monday to Friday, from 08:00 to 15:00.
To book your passage, please give us a call on 03030 404040 and our team will be happy to assist.